A project manager wants a high-level, early description of what is in and out of scope for the sponsor to approve before detailed planning. Which charter content serves this need?
- A
The final acceptance report
- B
The detailed work breakdown structure
- C
The preliminary scope statement
- D
The vendor performance review
Correct answer: C — Explanation
The preliminary scope statement gives a high-level view of included and excluded work, to be elaborated during planning. A detailed WBS, acceptance report, and vendor review are produced later.